Accessibility Options

Sitemap

Cliff Head Oil Field (WA-31-L, Australia)

HISTORY
  • In 2001, ROC’s first well drilled in Western Australia discovered the Cliff Head Oil Field, the first commercial oil discovery in the offshore Perth Basin.  The field has established the offshore Perth Basin as Australia’s fourth offshore oil producing region, after the Bass Strait, the North West Shelf and the Timor Sea.

  • The Cliff Head Field was declared commercial-in-principle in October 2003, the Field Development Plan was finalised in December 2004 and the Joint Venture made the Final Investment Decision for the project in March 2005.  Pipeline licences were granted in April 2005 and Production Licence WA-31-L over the field was granted in October 2005.

  • Production facilities construction and installation of pipelines, power cable and umbilical were successfully completed in November 2005.

  • The platform jacket was installed in December 2005 immediately after which development drilling commenced.  Topside installation was successfully completed in February 2006.

  • The BP crude oil unloading facility at Kwinana was officially opened in February 2006 and commissioning of the Arrowsmith Stabilisation Plant ("ASP"), which receives the oil produced from the field, was completed end-April 2006.
  • Production commenced on 1 May 2006, less than 14 months after project sanction, at an initial controlled clean-up rate of approximately 1,000 barrels of oil per day ("BOPD").
  • The first export of crude oil from the ASP was delivered to the BP Kwinana Unloading Facility on 5 May 2006.
  • Development drilling of six production wells and two water injection wells was completed on 16 July 2006, after which  the field produced at a better than expected rate, with only four of the six production wells on stream producing an average of 12,500 BOPD.  The remaining two oil production wells were completed by 23 July 2006.
  • The field achieved a significant milestone in September 2006 when cumulative oil production exceeded one million barrels.  In December 2006, the field produced its two millionth barrel of oil.
  • In May 2007, oil production from the field achieved its production target of 3.0 MMBO in the first year of production and in September 2007, the field produced its 4 millionth barrel of oil representing 22,450 man days without a Lost Time Injury.
  • In November 2007, 18 months after production commenced, the field produced in 5 millionth barrel of oil and paid out its $327 million capital cost.
GEOLOGY

The field has the following key geological features:

  • Reservoir: stacked series of Permian sands.
  • Trap: fault- and dip-closed structure.
  • Seal: early Triassic Kockatea shale.
DEVELOPMENT PLAN AND FACILITIES

Facilities consist of the following:

  • A jack-up installed, unmanned, remotely operated wellhead platform connected by pipelines to onshore processing facilities at Arrowsmith.
  • Two steel 273mm diameter pipelines, 14km long; one for production fluids, one for water injection.
  • A 14km power cable for general platform power, specifically for powering electric submersible pumps in the production wells.
  • A 14km chemical injection umbilical for corrosion and scale inhibition.
  • Oil is trucked to the BP refinery at Kwinana. 

Activity Status
  • Producing
Project Capital Investment to First Oil
  • A$327MM gross (ROC net A$123MM)
Remaining 2P Reserves
  • ROC net 3.5 MMBO at 30 June 2008
First Production
  • 1 May 2006
Average Gross Production Rate for Quarter Ending 30 September 2008
  • 5,958 BOPD (ROC net 2,234 BOPD)
JV Participants
Roc Oil (WA) Pty Limited (Operator) 37.5%
AWE Oil (Western Australia) Pty Ltd 27.5%
ARC (Offshore PB) Limited 30.0%
CIECO Energy Australia Pty Ltd 5.0%